South Beach Development Stage 4 Remediation
Client: Stockland
Location: South Beach, WA
Start Date: October 2009
End Date: December 2009
Value: $0.43 million
South Beach Development is located 2 kilometres from the Fremantle Café strip, along the northern Cockburn coastline.
Brierty were contracted to complete the remediation works for the former train refuelling site for future development.
The works included:
- Removal, testing and disposal to a suitable facility of hydrocarbon contaminated material;
- Removal and disposal of redundant drainage system;
- Removal and reuse of existing limestone sub-base;
- Removal and reuse of uncompacted fill to achieve finished level ready for development;
- Detailed earthworks;
- Traffic management; and
- Stakeholder engagement