Western Turner Syncline Stage 2

Client: Rio Tinto
Location: Tom Price, WA
Start Date: June 2014
End Date: December 2018
Value: $300 million

The Western Turner Syncline Stage 2 (WTS2) project is located 12kms East of Rio Tinto’s existing Western Turner Syncline Stage 1 project West of Tom Price. The WTS2 project is a greenfields operation requiring the establishment of site access roads, non process infrastructure and haul roads. 

Read more

Karara Open Pit Mining Hematite

Client: Karara Mining Ltd
Location: Perenjori, WA
Start Date: June 2011
End Date: November 2014
Value: $250 million

The Karara Iron Ore project, situated in the Midwest region of Australia, is a joint venture between Gindalbie Metals and Chinese steel producer AnSteel.

Read more

Tanami Gold - Bald Hill

Client: Tanami Gold NL
Location: Kimberley Region, WA
Start Date: November 2010
End Date: December 2011
Value: $12.4 million

Located 14km from the WA border, the scope of work includes drill and blast and load and haul of approximately 3,200,000m3 of material from Kookaburra and Sandpiper pits, over an eleven month period.

Read more

Extension Hill

Client: Mount Gibson Iron
Location: Midwest Region, WA
Start Date: December 2010
End Date: June 2011
Value: $5.7 million

The scope of works included the clearing, pioneering, and load and haul of ore and waste material at the Open Pit Hematite Mine.

Read more

Pillara Mine Rehabilitation

Client: Lennard Shelf Pty Ltd
Location: 25km south east of Fitzroy Crossing, WA
Start Date: March 2010
End Date: October 2010
Value: $9.5 million

Brierty was contracted to complete the rehabilitation works at Pillara Lead and Zinc Mine for Lennard Shelf Pty Ltd, jointly owned by Xstrata and Teck Resources. The mine is located approximately 25km south east of Fitzroy Crossing in the Kimberley region of Western Australia.

Read more

Tanami Gold - Coyote

Client: Tanami Gold NL
Location: Coyote Mine, WA

Start Date: December 2008

Date: June 2010
Value: $11 million

Coyote is an open pit mining operation located on a remote site about 300km south east of Halls Creek near the Northern Territory border.

Read more

FMG Cloudbreak

Client: Fortescue Metals Group
Location: 250km south of Port Hedland, WA
Start Date: September 2008
End Date: February 2009
Value: $35 million

The Cloudbreak mining operation represents the initial phase of Fortescue’s iron ore mining activities. The mine and ore processing facilities are located in the east Pilbara region of Western Australia, 150km north of Newman. The access road for Cloudbreak mine is via Marble Bar-Newman Road and north of the Roy Hill Station homestead.

Read more

Copernicus Open Pit & Ore Haulage

Client: Copernicus Nickel Mines Pty Ltd
Location: 150km south of Hall Creek, WA
Start Date: June 2008
End Date: December 2008
Value: $11 million

Brierty was contracted by Panoranic Resources to undertake the open pit mining at Copernicus Pit. 

Read more

Indee Gold

Client: Range River Gold
Location: West Pilbara, WA
Start Date: March 2006
End Date: March 2008
Value: $20 million

The Indee Gold Project is located approximately 80km south west of Port Hedland, 25km north of Whim Creek and 8km east from the North West Coastal Highway in Western Australia.

Read more

Telfer Treatment Ponds

Client: Newcrest Mining Limited
Location: Telfer, WA
Start Date: March 2006
End Date: September 2006
Value: $0.5 million

The project involved civil works associated with the Telfer Treatment Ponds

Read more

Telfer Tailings Storage Facility 7

Client: Newcrest Mining Limited
Location: Telfer, WA
Start Date: July 2006
End Date: September 2006
Value: $3 million

Brierty undertook the construction of the Stage 2 downstream raising of the perimeter embankment associated with Tailings Storage Facility 7 located at Newcrest’s Telfer Gold Mine.

Read more

Telfer Underground Access Road

Client: Newcrest Mining Limited
Location: Telfer, WA
Start Date: May 2006
End Date: June 2006
Value: $2.2 million

This project involved the construction of an underground haul road approximately 1700m in length.

Read more

Telfer Mine Various Projects

Client: Newcrest Mining Limited
Location: Telfer, WA
Start Date: September 2003
End Date: June 2006
Value: $60+ million

Brierty was initially contracted in September 2003 to provide stabilisation to 84 floodways of the Telfer Access Road. Newcrest Mining opted to engage Brierty Contractors as its major civil contractor for the infrastructure upgrade.

Read more

Woodie Woodie Mine Infrastructure

Client: Consolidated Minerals
Location: Woodie Woodie, WA
Start Date: August 2004
End Date: October 2005
Value: $8.5 million

Various contracts have been undertaken at Woodie Woodie comprising tailings dam, rehabilitation, removal of overburden, airport runway construction and road reconstruction and overlay works.

Read more

Sally Malay Storage Facilities

Client: Roche Mining for Kimberley Nickel Mines
Location: Sally Malay, WA
Start Date: April 2004
End Date: July 2004
Value: $4 million

Sally Malay mine is located in the East Kimberley region of Western Australia, 240km south of Kunnunurra.

Read more