
Telfer Treatment Ponds
Client: Newcrest Mining Limited 
Location: Telfer, WA
Start Date: March 2006
End Date: September 2006
Value: $0.5 million
The project involved civil works associated with the Telfer Treatment Ponds including:
- Clearing and topsoil stripping;
- Load and haul of borrow material for embankment earthworks;
- Construction of a new lined primary treatment pond;
- Construction of a new unlined evaporation pond;
- Diversion drains;
- Raising and trimming of the existing embankments to defined levels;
- Placement of gravel sheeting to the new and existing embankments;
- Removal of existing perimeter fencing to the east side of the existing ponds;
- Construction of a new fence to match existing;
- Supplying of all as-constructed records for the project; and
- Management of construction sequences, pond water levels and bypass flows








