Delivering civil construction and mining services solutions with certainty








Client Newmont Gold Corporation
EPCM Aker Kvaerner Clough Murray & Roberts Joint Venture
Location Boddington, WA
Start Date October 2006
End Date Current
Value $38.6M
This project, part of the Boddington Gold Mine Expansion Project, comprises the works associated with the earthworks, roads and drainage for construction of the new Boddington Gold Mine Process Plant, situated at the end of Soldiers Road.
Client BGM Management Company Pty Ltd
Location Boddington Gold Mine, Southwest WA
Start Date September 2007
End Date May 2008
Value $18.6M
This project is part of the Boddington Gold Mine Expansion Project. Works include: clearing topsoil, bulk earthworks, clay lining, residue disposal area and tailings system.
Client Newmont Gold Corporation
EPCM Aker Kvaerner Clough Murray & Roberts Joint Venture
Location Boddington, WA
Start Date April 2006
End Date October 2006
Value $5M
This project, part of the Boddington Gold Mine Expansion Project, comprises the works associated with the bulk earthworks for the new accommodation village, situated on Old Soldiers Road, and the preloading earthworks at selected areas within the plant site as part of the Boddington Gold Mine Expansion Project.
Read more: Boddington Accommodation Village & Preload Earthworks
Client Mount Gibson Iron Limited
Location Koolan Island, WA
Start Date December 2007
End Date September 2008
Value $15M
The Koolan Island hematite mining operation is in Yampi Sound, off the northern Kimberley coast of Western Australia. Almost 70 million tonnes of high grade (Fe @ 67%) iron ore was mined by BHP from Koolan Island from 1959 to 1993. Hematite production at Koolan Island recommenced in early 2007 with the first shipment achieved in June 2007.
Client Fortescue Metals Group
Location Port Hedland, WA
Start Date October 2008
End Date February 2009
Value $ 40M
Located at Port Hedland, works on the project commenced in July 2008 and involves the construction of reclamation bunds to hold dredged material, construction of the earthwork foundations for stacker and reclaimer infrastructure and general miscellaneous earthworks required to manage the facility.
Client Fortescue Metals Group
Location Port Hedland, WA
Start Date June 2007
End Date March 2008
Value $50M
Brierty completed works for Fortescue Metal Group’s Pilbara Iron and Infrastructure Rail Project, an integral part of the new infrastructure to support the development and sale of the Cloud Break and Christmas Creek iron ore deposits.
Client: BHP Billiton
Location: Ravensthorpe, WA
Start Date: March 2006
End Date: May 2007
Value: $31.1 million
This project comprised the clearing and pre-stripping of topsoil and construction of haul roads and includes:
Client Newcrest Mining Limited
Location Telfer, WA
Start Date May 2006
End Date June 2006
Value $2.2M
This project involved the construction of an underground haul road approximately 1700m in length.
Client Newcrest Mining Limited
Location Telfer, WA
Start Date March 2006
End Date September 2006
Value $0.5M
Civil works associated with the Telfer Treatment Ponds including:
Client Newcrest Mining Limited
Location Telfer, WA
Start Date July 2006
End Date September 2006
Value $3M
Construction of the Stage 2 downstream raising of the perimeter embankment associated with Tailings Storage Facility 7 located at Newcrest’s Telfer Gold Mine.
Client Newcrest Mining Limited
Location Telfer, WA
Start Date September 2003
End Date December 2004
Value $15M
The construction of Stage 1 of the Tailings Storage Facility is one several projects undertaken by Brierty to upgrade the infrastructure at Telfer. The works involved approximately 1,000,000m3 of bulk earthworks.
Client Newcrest Mining Limited
Location Telfer, WA
Start Date September 2003
End Date June 2006
Value $60M+
Brierty Contractors was initially contracted in September 2003 to provide stabilisation to 84 floodways of the Telfer Access Road. Newcrest Mining opted to engage Brierty Contractors as its major civil contractor for the infrastructure upgrade.
Client Water Corporation
Location Harvey, Southwest WA
Start Date November 1999
End Date April 2000
Value $32M
The Harvey Dam Forward Works were undertaken in an alliance contract with the Water Corporation, known as the Stirling Alliance. The project was identified as suitable for this type of arrangement due to the degree of difficulty of the works and environmental constraints.