Delivering civil construction and mining services solutions with certainty








Client Newmont Gold Corporation
EPCM Aker Kvaerner Clough Murray & Roberts Joint Venture
Location Boddington, WA
Start Date April 2006
End Date October 2006
Value $5M
This project, part of the Boddington Gold Mine Expansion Project, comprises the works associated with the bulk earthworks for the new accommodation village, situated on Old Soldiers Road, and the preloading earthworks at selected areas within the plant site as part of the Boddington Gold Mine Expansion Project.
Works included carrying out earthworks, drainage and preliminary roadworks for new 1,800 person accommodation village including:
Supply of all materials for the works
Carrying out of all preloading earthworks required on selected areas within the plant site using preload material provided including: