Transport Infrastructure

FMG Access Road

E-mail

fmg-access-roadClient: Fortescue Metals Group (FMG)
Location: Port Hedland, WA
Start Date: October 2009
End Date: January 2010
Value: $3.5 million

Brierty will construct the upgrade of 2km access road over a 12 week period. The access road will support FMG’s port infrastructure operations.

Read more: FMG Access Road

   

Port Hedland Intersection Upgrade

E-mail

port-hedland-intersectionsClient Main Roads WA
Location Port Hedland, WA
Start Date June 2009
End Date Current
Value $6.7M

The works comprise realignment, reconstruction and widening of Great Northern Highway and associated side roads in the town of Port Hedland between Goldsworthy Rail Crossing and Bell Street.

Read more: Port Hedland Intersection Upgrade

   

Utah Point Access Road

E-mail

utahClient Port Hedland Port Authority
Location Port Hedland, WA
Start Date June 2009
End Date Current
Value $12.5M

Brierty will construct the 8.5km access road over a 25 week period. The access road will support the new $225 million Public Access Berth at Utah Point currently under construction in the Port Hedland Inner Harbour.

Read more: Utah Point Access Road

   

Access Alliance

E-mail

accessClient Main Roads WA
Location Muchea to Bindi Bindi, Western Australia
Start Date October 2007
End Date Current
Value $100M +

The current program involves upgrading Great Northern Highway between Muchea and Bindi Bindi in Western Australia’s wheatbelt. Our works include reconstruction and widening, realignment of substandard sections, construction of new passing lanes, intersection upgrades and improvements to roadside amenities including...

Read more: Access Alliance

   

ALine East

E-mail

alineClient Main Roads Western Australia
Location
Central Eastern Wheatbelt, WA
Start Date
June 2005
End Date
February 2008
Value
$48M

The project was undertaken by an innovative partnership between the WA State Government and private enterprise. Known as the ALine East Alliance, the consortium includes representatives from Main Roads Western Australia (MRWA), Brierty Contractors, BG&E and WML Consultants.

Read more: ALine East

   

Dampier Highway Stage 1B

E-mail

DampierClient Main Roads WA
Location
Karratha / Dampier, WA
Start Date August 2007
End Date
July 2008  
Value $8.8M

This project was a major Cat 2 delivery contract for Main Roads WA Pilbara Region. It duplicated the Dampier Highway in Karratha townsite to cater for the resources boom placing 15,000vpd between Dampier and Karratha.

Read more: Dampier Highway Stage 1B

   

Leach / Orrong Road Intersection Upgrade

E-mail

leachClient John Holland
Location
Perth, WA
Start Date
January 2006
End Date
March 2007
Value
$17 million

Brierty was subcontracted to John Holland to undertake the civil works for this R5 category project.

Read more: Leach / Orrong Road Intersection Upgrade

   

New Metro Rail Package C

E-mail

packcClient Public Transport Authority of WA
Location
Perth, WA
Start Date
June 2005
End Date
December 2006
Value:
$32M

The project was undertaken by the joint venture between Doric and Brierty. The project scope involves the construction of two stations...

Read more: New Metro Rail Package C

   

New Metro Rail Package B

E-mail

packbClient Public Transport Authority of WA
Location
Perth, WA
Start Date
June 2005
End Date
December 2006
Value
$32M

The project was undertaken by the joint venture between Doric and Brierty.

Read more: New Metro Rail Package B

   

Quinns Road Bridge

E-mail

quinnsClient Public Transport Authority of WA
Location
Perth, WA 
Start Date August 2003 
End Date May 2004 
Value $3.5M

The project scope included the investigation, design and construction of...

Read more: Quinns Road Bridge

   

Term Network Contracts 3 & 7

E-mail

tncClient Works Infrastructure (Emoleum) 
Location Various locations, WA

 

 

Pavement repairs and minor improvement works to various highways in the Wheatbelt area.

Completed projects include reconstruction of Great Northern Highway in Bindoon, Mingenew Morawa Road pavement repairs and Geraldton to Mt Magnet Road widening and Brand Highway pavement rehabilitation.

Read more: Term Network Contracts 3 & 7